Project Management
- You are organizing an Annual Day in your university. Explain the steps to designing a project organization structure for this case. According to you which will be the most critical steps and why?
Ans 1.
- India’s Road and Transport Ministry has taken up various Expressway Road Projects in the country. One of the such project consist of following parts
- Constructing roads
- Constructing tunnels
- Constructing bridges over the river
- Constructing flyovers and junctions
- Constructing convenient places (fuels stations, rest areas, etc.)
- Developing a solution for speed monitoring
- Finding suitable road material for areas in a heavy flood zone
Using thing information as example, describe various project life cycle models
Ans 2.
- A project manager is struggling to manage the project due to risk and the cost. The details are
Original Project Budget: Rs. 40, 00,000
- Original Estimated Duration: 36 Months
- Elapsed Time: 12 Months
- Money Spent till Date: Rs. 15,00,000
- Work Completed: 40 %
- Risk Identified and Ratings
- Suggest the risk priority to this project manager.
Ans 3a.
- Find out the “Estimate at Completion” using all possible ways.
Ans 3b.